ENERGY STAR Process… Step by Step
Momentum conducts 5 different tests & inspections during your building process.
LOCALLY OWNED & OPERATED
Momentum conducts 5 different tests & inspections during your building process.
Please send your Plans, Manual J, and Job Schedule to Monica at billing@momentumidaho.com
(Rough-In Inspections)
Visit 1: Inspect energy seal – determines that duct leakage falls within required parameters. *Ducts must be completely assembled & sealed before we can administer this test.
Visit 2: Perform duct blaster – ensure all penetrations are caulked and/or foam-filled. *After the Air Seal has been completed by your insulation company.
These Required Checklists Should Be Started
Idaho is under the National ENERGY STAR Version 3.0
*After the walls have been insulated and before the drywall goes up.
*Usually scheduled right before the final clean.
If additional inspections are required, Momentum will notify builder as soon as possible.
*The person who needs to complete the checklist is listed in red.
National Rater Design Review Checklist (Builder + Momentum)
National Rater Field Checklist (Momentum)
National HVAC Design Report (Your HVAC Designer)
National HVAC Commissioning Checklist (Your HVAC Installer)
National Water Management System Builder Requirements (Builder)
As part of the ENERGY STAR building process, Momentum is involved in the design phase and performs framing inspections, insulation inspections, final testing, and certification. Momentum is there to ensure that all the pieces come together and the final product will be a comfortable home that is as energy efficient as possible. It truly is a partnership throughout the entire ENERGY STAR build process.